Contract Owner | The Airline of the Islamic Republic of Iran |
Project Description:
• Construction of the building for the main central heating plant (2000 square), • Procurement and installation of three absorption chillers (EBARA), each with 800 ton capacity. • Procurement and installation of three Packman boilers with 19 million BTU as well as three • installation of steel pipes; total installed OD surface area = 150000 inches • 40 km of Structured cabling • Installation of various equipment such as cooling towers, pumps, expansion tanks, water |